Category:
Walsh were appointed by Dreadnought to undertake works for their factory extension in April 2019. The project included extensive earthworks and muckshift, a 5m high retaining wall, piling works, sub structure machine pits and associated works.
Over the last 2 years Walsh Construction in a main contractor role have worked at Dreadnought Tiles on creating a factory extension for their manufacturing business. These works included entrance works, temporary haul roads, earthworks, steel piles, creating a concrete slab, 5m high retaining wall, and sub structure machine pit works. During this time Walsh have worked with Sub Contractors in specialist trades such as pilers, cladders, roofers, metal fabricators and bespoke steel work specialists.